| Purpose: Cleanup CERCLA Lead: PRP--Ketchikan Pulp |
Contaminant: PAHs |
| USACE Role: Technical review of feasibility study. | |
| Technical Issues: Wood debris in deep water makes dredging difficult, no disposal site available near by. | |
| Back to map | |
| Purpose: Cleanup Lead: State AK |
Contaminant: PAHs |
| USACE Role: Technical review of feasibility study. | |
| Technical Issues: Wood debris in deep water makes dredging difficult, no disposal site available near by. | |
| Back to map | |
| Purpose: Navigation Lead: San Francisco District |
Contaminant: Metals, butylins, PAHs Vol Dredged Material: Channel Deepening |
| USACE Role: Contaminant pathway testing and evaluations, disposal facility design requirements. | |
| Technical Issues: Containment releases for confined disposal facilities | |
| Products: Miscellaneous Paper EL-93-17. View on-line or download part1.exe and part2.exe | |
| Back to map | |
| Purpose: Navigation Lead: USACE Los Angeles District |
Contaminant: Metals, organics Vol Dredged Material: 500,000+ cu yd |
| USACE Role: Design and construct. | |
| Technical Issues: Effective cap design, convince local public that capping environmentally protective. | |
| Back to map | |
| Purpose: Navigation Lead: San Francisco District |
Contaminant: PAHs, PCBs, organotins, pesticides, metals Vol Dredged Material: Channel Deepening |
| USACE Role: Contaminant bioavailability from bedded and suspended Oakland Harbor Deepening Project Sediments. | |
| Technical Issues: Continued use of in-bay DM disposal sites. Relative avialability of contaminants in re-suspended DM and in bedded DM. Comparisons of contaminated sediments outside dredged channel with Central SF Bay surficial sediments re-suspended by wave action. | |
| Products: Miscellaneous Paper EL-94-7. View on-line or download part1.exe and part2.exe | |
| Back to map | |
| Purpose: Navigation Lead: San Francisco District |
Contaminant: Metals, butyltins, PAHs, PCBs Vol Dredged Material: Channel Deepening |
| USACE Role: Contaminant pathway testing and evaluations, disposal facility design requirements. | |
| Technical Issues: Contaminant releases for confined disposal facilities. | |
| Products: Miscellaneous Paper EL-92-12, Vol 1 and 2 | |
| Back to map | |
| Purpose: Cleanup Natural Resource Trustee Lead: NOAA |
Contaminant: DDT, PCBs Vol Dredged Material: 17 sq km contaminated area |
| USACE Role: Planning level feasbility study, design requirements for insitu and dredging options, assessment of deep water dredging technologies. | |
| Technical Issues: Vast area and volume to be remediated, water depths 30 to 200 m, implementability issues for dredging. | |
| Products: 1994 Expert Report for NOAA/DOJ | |
| Back to map | |
| Purpose: Cleanup Lead: USEPA Region 9 |
Contaminant: DDT, PCBs |
| USACE Role: Study of capping options for EECA including contaminant pathway testing, modeling for cap placement, cap stability and cap effectiveness. | |
| Technical Issues: Selection of capping areas, cap design, equipment and techniques for cap placement, ability to construct cap in deep water, cap erosion potential, seismic stability, long term flux of contaminants through cap, monitoring requirements. | |
| Products: Technical Report EL-99-2 | |
| Back to map | |
| Purpose: Navigation Lead: San Francisco District |
Contaminant: Metals, butyltins, PAHs Vol Dredged Material: Channel Deepening |
| USACE Role: Contaminant pathway testing and evaluations, disposal facility design requirements. | |
| Technical Issues: Contaminant releases for confined disposal facilities | |
| Products: Miscellaneous Paper EL-93-18 | |
| Back to map | |
| Purpose: Navigation Lead: U.S. Navy PACDIV |
Contaminant: Metals, PAHs Vol Dredged Material: Periodic Maintenance |
| USACE Role: Multi-Phase Dredged Material Management Plan, testing and evaluations, disposal facility design requirements. | |
| Technical Issues: Water quality certification requirements, retention effectiveness of confined disposal facility, land disposal regulations. | |
| Products: ERDC/EL SR-00-3, ERDC/EL SR-00-4, ERDC/EL SR-00-5 | |
| Back to map | |
| Purpose: Navigation Lead: Chicago District |
Contaminant: PCBs |
| USACE Role: CDF Management | |
| Technical Issues: Re-mobilization and distribution of PCBs in disposed material to fish and invertebrate organisms colonizing CDF. Comparisons with residues in organisms collect from River and navigation channel sites. | |
| Products: 1994 Report to Chicago District | |
| Back to map | |
| Purpose: Navigation Lead: Chicago District |
Contaminant: Metals, PAHs, PCBs Vol Dredged Material: 200,000 cy |
| USACE Role: Field demonstration of dredging technologies, contaminant pathway testing and evaluations, formulation of alternatives, disposal facility design requirements. | |
| Technical Issues: Modeling for no action option, contaminant releases for dredging resuspension, uplnd and nearshore confined disposal facilities and contained aquatic disposal sites, TOSCA disposal requirements. | |
| Products: Miscellaneous Paper EL-87-9, Vol 1 and 2 | |
| Back to map | |
| Purpose: Cleanup CERCLA Lead: USEPA Region 5 |
Contaminant: PCBs Vol Dredged Material: 100,000+ cu yd |
| USACE Role: Technical review, HQEPA Interagency Review Panel. | |
| Technical Issues: Contaminant release during dredging, feasibility of meeting cleanup goals by dredging versus in-situ capping. | |
| Products: 1995 Interagency Review Panel Report to HQEPA | |
| Back to map | |
| Purpose: Navigation Lead: Detroit District |
Contaminant: Metals, PCBs Vol Dredged Material: Annual Maintenance |
| USACE Role: Field monitoring and laboratory testing. | |
| Technical Issues: Concentrations of contaminants in hopper dredge overflow, ability to continue overflow practices, retention effectiveness of confined disposal facility. | |
| Products: Miscellaneous Paper D-89-3, Miscellaneous Paper EL-91-4 | |
| Back to map | |
| Purpose: Navigation Lead: USACE Detroit District |
Contaminant: PCBs |
| USACE Role: CDF management. | |
| Technical Issues: Biotreatment effectiveness investigated with field pilot study, results being evaluated. | |
| Back to map | |
| Purpose: Naviagtion Lead: HQ USACE, New England District, EPA Narragansett Lab |
Contaminant: Metals, PCBs Vol Dredged Material: Pilot Placement sites for upland, wetland, and aquatic |
| USACE Role: Contaminant pathway testing and evaluations, and field sampling for validation of laboratory based predictions. | |
| Technical Issues: Contaminant releases and environmental effects for upland, wetland and aquatic disposal environments. Validation of laboratory testing protocols. | |
| Products: Technical Report D-88-5, Technical Report D-88-6, Technical Report D-88-7, Technical Report D-89-2 | |
| Back to map | |
| Purpose: Cleanup RCRA Lead: USEPA Region 1, New England District |
Contaminant: PCBs Vol Dredged Material: 60,000 cu yd |
| USACE Role: Removal Action Design and Construct, screening model, remedial investigation, technical oversight. | |
| Technical Issues: Contaminant release during dredging, dredging technology, habitat and river restoration, wetlands protection, cleanup standards, disposal. | |
| Back to map | |
| Purpose: Cleanup RCRA Lead: PRP -- General Electric, New England District |
Contaminant: PCBs Vol Dredged Material: 15,000 cu yd plus in-situ capping |
| USACE Role: Technical review and oversight for Upper half mile and Silver Lake. | |
| Technical Issues: Source control, groundwater modeling, groudwater cleanup, dredging technology, subaqueous cap design, river restoration, treatment and disposal. | |
| Back to map | |
| Purpose: Cleanup RCRA Lead: USEPA Region 1 |
Contaminant: PCBs |
| USACE Role: Technical review and oversight for Upper Reach Lower River. | |
| Technical Issues: Dredging technology, subaqueous cap design, river restoration, treatment and disposal. | |
| Back to map | |
| Purpose: Cleanup CERCLA Lead: USEPA Region 1, New England District |
Contaminant: PCBs, heavy metals Vol Dredged Material: 500,000 cu yd |
| USACE Role: Full Engineering Feasability Study including field demonstration of dredging equipment, contaminant pathway testing and evaluations, disposal facility design requirements. | |
| Technical Issues: High PCB concentrations, contaminant transport and release during dredging, dredging efficiency, water treatment, volatile emissions, contaminant releases for upland and nearshore confined disposal facilities and contained aquatic disposal sites. | |
| Products: Technical Report EL-88-15 Vols. 1-12 | |
| Back to map | |
| Purpose: Cleanup CERCLA Lead: U.S. Navy |
Contaminant: PAHs, PCBs, metals |
| USACE Role: Technical review of feasibility study. | |
| Technical Issues: Debris from landfill in Narragansett Bay makes dredging difficult to implement, regulatory agencies oppose capping--habitat loss, RCRA disposal issue based on derived from rule although relatively low contaminant concentrations, RCRA issue escalates disposal costs. | |
| Cleanup Approach: RCRA. | |
| Back to map | |
| Purpose: Cleanup CERCLA Lead: PRP--Alcoa |
Contaminant: PCBs |
| USACE Role: Technical review and construction oversight. | |
| Technical Issues: Contaminant release during dredging, dredging technology, PRP want to cap rather than dredge. | |
| Back to map | |
| Purpose: Navigation Lead: New York District |
Contaminant: PCBs, dioxins, chlorinated HCs, metals, other priority pollutants |
| USACE Role: Characterization of reference site contamination status for Green Book regulatory evaluations | |
| Technical Issues: Biota/sediment accumulation factors (BSAFs) for comprehensive list of sediment contaminants. | |
| Products: 1994 Report to New York District | |
| Back to map | |
| Purpose: Navigation Lead: USACE New York District |
Contaminant: Dioxins, organics, metals Vol Dredged Material: 5,000,000 cu yd per yr |
| USACE Role: Contaminant pathway testing, site selection studies, GIS development, modeling, design study for contained aquatic disposal. | |
| Technical Issues: Select and design alternate disposal facilities in lieu of open water disposal. | |
| Products: Reports in preparation | |
| Back to map | |
| Purpose: Navigation Lead: USEPA Region 2 |
Contaminant: Dioxins, organics, metals Vol Dredged Material: 1,000+ cu yd pilot demonstrations |
| USACE Role: Sediment Decontamination Demonstration Program. | |
| Technical Issues: Evaluate technologies for NY/NJ Harbor sediments, cost effectiveness, implementability, regulatory approval of thermal process. | |
| Products: Miscellaneous Paper EL-94-1 | |
| Back to map | |
| Purpose: Navigation Lead: U.S. Navy LANTDIV |
Contaminant: Metals, PCBs Vol Dredged Material: Periodic Maintenance |
| USACE Role: Contaminant pathway testing and evaluations, formulation of alternatives, management plan development. | |
| Technical Issues: Long term capacity for contaminated dredged material, disposal site selection, design requirements, contaminant releases, beneficial use applications. | |
| Products: Miscellaneous Paper EL-90-8, Miscellaneous Paper EL-93-1 | |
| Back to map | |
| Purpose: Cleanup CERCLA Lead: EPA Region 10, Seattle District |
Contaminant: Metals, PAHs, PCBs Vol Dredged Material: Multiple Operable Units |
| USACE Role: Development of a technical decisionmaking framework for contaminant pathways. | |
| Technical Issues: Largest Superfund site in the U.S., contaminant releases for nearshore and upland confined disposal facilities and subaqueous capped sites. | |
| Products: Miscellaneous Paper D-91-1. View on-line or download part1.exe and part2.exe. | |
| Back to map | |
| Purpose: Navigation Lead: U.S. Navy WESDIV, Seattle District |
Contaminant: Metals, PCBs Vol Dredged Material: 3,300,000 cy |
| USACE Role: Contaminant pathway testing and evaluations, formulation of alternatives, disposal facility design requirements. | |
| Technical Issues: Modeling for capping options, containment releases for dredging resuspension, upland and nearshore confined disposal facilities and subaqueous capped sites. | |
| Products: Technical Report EL-89-1. View on-line or download part1.exe and part2.exe. | |
| Back to map | |
| Purpose: Cleanup CERCLA Lead: PRP--Occidental |
Contaminant: VOCs, PAHs |
| USACE Role: Technical review of feasibility study. | |
| Technical Issues: Contaminant release during dredging, source control, mixing zones, contaminant transport. | |
| Back to map | |
| Purpose: Cleanup and Navigation Lead: State WA and USACE Seattle District |
Contaminant: Metals, organics Vol Dredged Material: 500,000 cu yd per yr |
| USACE Role: Identification and Conceptual Designs for Disposal Options. | |
| Technical Issues: Design of a mixed material confined disposal option for navigation dredged material and sediment cleanup, diked disposal and subaqueous confined. | |
| Products: ERDC TR-00-3 | |
| Back to map | |
| Purpose: Cleanup CERCLA Lead: PRP |
Contaminant: PAHs, metals Vol Dredged Material: 400,000 cu yd |
| USACE Role: Technical review of feasibility study. | |
| Technical Issues: Disposal site design, contaminant transport. | |
| Back to map | |
| Purpose: Navigation Lead: USACE Detroit District |
Contaminant: PAHs |
| USACE Role: CDF management. | |
| Technical Issues: Experimenting with techniques to accelerate biodegradation of organic contaminants, use treated dredged material beneficially, reclaim CDF capacity. | |
| Back to map | |
| Purpose: Navigation Lead: Detroit District |
Contaminant: PCBs |
| USACE Role: Contaminant bioavailability to freshwater fish and mollusks. | |
| Technical Issues: Influence of winter and summer extremes of water temperature on bioaccumulation of PCBs from dredged channel sediments. | |