Fiscal Year: 1999
|
Project Dates: 2/10/99 - 3/24/99
|
|
Contract Number: DAC21-99-0003
|
|
Project Description: N/A
|
|
Maintenace / New Work: Maintenance
|
Federal / Regulatory: Federal
|
|
Total Project Cubic Yards: 948158
|
Total Days of Dredging: 0
|
Total Hours of Dredging: 0
|
|
|
Type of Material: Mud, sand, clay, shell
|
Disposal Method(s) for Material: Open Ocean Disposal Area
|
|
Total Turtle Takes: 5
|
|
|
Observer Company Used: Coastwise Consulting, Inc.
|
Relocation Trawling? Yes
2/28-3/20, started at 0829 on load #112. During the towing operation, 13 cc and 4 lk were relocation during the 215 tows that were performed.
|
|
Relocation Company: Dave Nelson, USACE-WES; Georgia Bulldog, Captain Lindsey Parker
|
|
Loggerheads: 14
|
Greens: 0
|
|
Kemp's Ridley: 4
|
Leatherbacks: 0
|
|
Hawksbill: 0
|
|
|
Total number turtles relocated: 18
|
Are Relocation Reports Available? Yes
|
|
Are Dredging Records Available? No
|
Are original turtle take data still available? Yes
|
|
Description of mitigation measures/dates used: Deflectors, relocation trawling (2/29/99-3/20/99)
|
|
Other Remarks: Based on daily reports it appears that turtle observing did not begin until load #45 on 2/20/99 while whale observing began with the first load.
There were also 14 incidents not attributed as a dredge take; many parts of same turtles found within different loads (see reports below of 'Non-Take Incidents').
|