Fiscal Year: 2007
|
Project Dates: 2/24/07 - 4/24/07
|
|
Contract Number: W912P8-07-C-0041
|
|
Project Description: On February 24, 2007, the NEWPORT began work in the Mile -0.2 to Mile -9.3 bar channel reach. The required depth of dredging was -43 feet Mean Low Gulf (MLG) and the
dredging width was 800 feet (full cut). All work was performed in either the agitation mode (5,185,188 cys), or in the dredge and haul mode with disposal into the ocean dredged material disposal site(ODMDS-197,618 cys) .
|
|
Maintenace / New Work: Maintenance
|
Federal / Regulatory: Federal
|
|
Total Project Cubic Yards: 5382806
|
Total Days of Dredging: 58
|
Total Hours of Dredging: 0
|
|
|
Type of Material: Mud, clay
|
Disposal Method(s) for Material: ODMDS and Agitation
|
|
Total Turtle Takes: 0
|
|
|
Observer Company Used: Coastwise Consulting
|