|
Fiscal Year: 2009
|
Project Dates: 8/28/09 - 9/12/09
|
|
Contract Number: W912P8-09-0320
|
|
Project Description: The hopper dredge Wheeler worked in the Calcasieu River bar channel - approximately between Mile -1.7 to Mile -6.1. Duration of project was 16 days. The Wheeler dredged 1,626,330 cy in the agitation mode (lots of "fluff" in the Calcasieu bar channel): about 80% agitation & 20% dredge and 566,233 cy in haul work. No trawling. REMSA providing the observers on board. In-house risk assessment concluded it was OK for the Wheeler to continue its dredging work at after take.
|
|
Maintenace / New Work: Maintenance
|
Federal / Regulatory: Federal
|
|
Total Project Cubic Yards: 2192563
|
Total Days of Dredging: 16
|
Total Hours of Dredging: 0
|
|
|
Type of Material: mud
|
Disposal Method(s) for Material: Agitation 80% and Dredge and hual 20%
|
|
Total Turtle Takes: 1
|
|
|
Observer Company Used: REMSA, Inc.
|