Fiscal Year: 2010
|
Project Dates: 4/26/10 - 6/22/10
|
|
Contract Number: W912P8-10-C-0030
|
|
Project Description: The hopper dredge Bayport began work in the Mile -1.8 to Mile -11.5 bar channel reach. The required depth of dredging was -44 feet Mean Low Gulf (MLG) and the dredging width was 800 feet (full cut). All work was performed in either the agitation mode, or in the dredge and haul mode with diposal into the ocean dredged material disposal site. During this period, the dredge worked a total of 58 days between bar channel indicated above. A total of 273 loads were collected. During this work period the Bayport removed at total of 6,014,562 cubic yards of material (5,185,012 cy by agitation and 829,550 cy by dredge and haul).
|
|
Maintenace / New Work: Maintenance
|
Federal / Regulatory: Federal
|
|
Total Project Cubic Yards: 6014562
|
Total Days of Dredging: 58
|
Total Hours of Dredging: 0
|
|
|
Type of Material: mud
|
Disposal Method(s) for Material: Agitation and ODMDS
|
|
Total Turtle Takes: 3
|
|
|
Observer Company Used: Coastwise Consulting, Inc.
|