Fiscal Year: 1996
|
Project Dates: 2/10/96 - 4/17/96
|
|
Contract Number: N/A
|
|
Project Description: Bar channel dredging between channel Miles -0.6 and -9.0.
|
|
Maintenace / New Work: Maintenance
|
Federal / Regulatory: Federal
|
|
Total Project Cubic Yards: 1177600
|
Total Days of Dredging: 65
|
Total Hours of Dredging: 0
|
|
|
Type of Material: Light, silty mud and clay
|
Disposal Method(s) for Material: Dredge & haul mode
|
|
Total Turtle Takes: 0
|
|
|
Observer Company Used: Coastwise Consulting
|